The tasks are carried out with the aim of improving the quality of life of residents and optimizing the treatment of sewage effluents. The construction of 1 sewage liquid pumping station, 990 meters of sewage liquid delivery pipe, 1 sewage liquid treatment plant composed of the compact treatment plant, slow filters, Parshall flume and contact chamber is contemplated.
The complementary works are electrical installations, single building, perimeter fence, water supply and internal roads.
It should be noted that it has an official budget of $259,125,883.31 and a completion period of 180 days.
Details of bidders:
-Proponent 1: APE SA – VIAL RG SA – COOPERATION CONSORTIUM
-Proponent 2: CONSTRUIINGENIERÍA SRL
-Proponent 3: COOPI – REGIONAL INTEGRAL COOPERATIVE FOR THE PROVISION OF PUBLIC SERVICES, HOUSING AND CONSUMPTION LIMITED
-Proponent 4: GRUPPI E HIJOS SA
-Proponent 5: PASCHINI SA
-Proponent 6: TECNAC SRL